Construction of the Larkspur Extension Project Update

 Author Sonamarine GM Report March 2018
Design is continuing to advance for the Larkspur Extension Project. Work on the Larkspur Station platform is underway. Workers have installed bridge protection slabs at the north and south ends of Unnamed Channel Bridge.
Rail welding and stockpiling is complete.Tie removal from Andersen to Rice Drive is complete.
PATHWAY
Paving, striping, and signage are complete at the pathway from North San Pedro to the CivicCenter Station. Work on the bike ramp is underway. Drainage measures are being added to the pathway from Franklin to Grant Avenue.
The construction of the pathway from the North Novato Station to Rush Creek Pathway is complete, wi th fencing installation underway.